Which of the following statements about NPV and IRR is FALSE?

a) The primary reason that the NPV method is conceptually superior to the IRR method for evaluating mutually exclusive investments is that multiple IRRs may exist, and when that happens, we don't know which IRR is relevant.
b) The NPV method's assumption that cash inflows are reinvested at the cost of capital is generally more reasonable than the IRR's assumption that cash flows are reinvested at the IRR. This is an important reason why the NPV method is generally preferred over the IRR method.
c) A project's IRR is independent of the firm's cost of capital. In other words, a project's IRR doesn't change with a change in the firm's cost of capital.
d) Conflicts between two mutually exclusive projects occasionally occur, where the NPV method ranks one project higher but the IRR method ranks the other one first. In theory, such conflicts should be resolved in favor of the project with the higher positive NPV.

User Gusa
by
8.7k points

1 Answer

3 votes

The false statement is about conflicts between two mutually exclusive projects and how they are resolved.

The false statement about NPV and IRR is option d) Conflicts between two mutually exclusive projects occasionally occur, where the NPV method ranks one project higher but the IRR method ranks the other one first. In theory, such conflicts should be resolved in favor of the project with the higher positive NPV.

User Ted Delezene
by
8.9k points