The false statement is about conflicts between two mutually exclusive projects and how they are resolved.
The false statement about NPV and IRR is option d) Conflicts between two mutually exclusive projects occasionally occur, where the NPV method ranks one project higher but the IRR method ranks the other one first. In theory, such conflicts should be resolved in favor of the project with the higher positive NPV.