Final answer:
The overhead assigned to Product A1 using Activity-Based Costing is $183,910, derived from calculating the costs for setups, machining hours, and packing orders specifically attributed to Product A1.
Step-by-step explanation:
To calculate the overhead assigned to Product A1 using Activity-Based Costing (ABC), we need to allocate the total overhead costs to each product based on the activities that drive those costs. There are three main cost pools: setup, machining, and packing.
- Setup Costs: The setup overhead rate per setup is $130,000 / 40 = $3,250. Product A1 has 19 setups, so its setup cost is 19 x $3,250 = $61,750.
- Machining Costs: The machining overhead rate per machine hour is $58,000 / 5,000 = $11.60. Product A1 has 4,100 machine hours, so its machining cost is 4,100 x $11.60 = $47,560.
- Packing Costs: The packing overhead rate per order is $92,000 / 500 = $184. Product A1 has 400 orders packed, so its packing cost is 400 x $184 = $73,600.
Adding up these costs, the total overhead assigned to Product A1 is $61,750 (setup) + $47,560 (machining) + $73,600 (packing) = $183,910.
Product A1 is assigned an overhead of $183,910 using Activity-Based Costing, calculated by summing up the costs allocated based on the number of setups, machining hours, and orders packed.