74.1k views
3 votes
You are considering the investment project summarized by the cash flows and timeline below. If the discount rate is 12%, what is the net present value of this project? Would you accept or reject the project? Year 0: cash outflow (cost) of $5,000 Year 1: cash inflow of $2,000 Year 2: cash inflow of $1,050 Year

User Bensw
by
6.5k points

1 Answer

5 votes

Final answer:

The net present value (NPV) of the project is -$2,376.56. The project should be rejected.

Step-by-step explanation:

The net present value (NPV) of this investment project can be calculated by discounting the cash flows to their present values and subtracting the initial cost. Let's calculate the NPV:

Year 0: Cash outflow = -$5,000

Year 1: Cash inflow = $2,000

Year 2: Cash inflow = $1,050

Now, discount each cash flow to its present value using the discount rate of 12%:

Present value of Year 0 cash outflow = -$5,000

Present value of Year 1 cash inflow = $2,000 / (1 + 0.12) = $1,785.71

Present value of Year 2 cash inflow = $1,050 / (1 + 0.12)^2 = $837.73

Calculate the total present value by adding the present values of all cash flows: PV = -$5,000 + $1,785.71 + $837.73 = -$2,376.56

The net present value (NPV) is -$2,376.56. Since NPV is negative, it means that the project's estimated value is less than the initial cost. Therefore, it is recommended to reject the project.

User Peter Watts
by
7.7k points