Final answer:
To decide on the investment, calculate the Net Present Value (NPV) for both Project A and Project B using the 8% hurdle rate. The project with the highest positive NPV is the preferred choice; if both have negative NPVs, neither should be chosen.
Step-by-step explanation:
To determine which project the company should invest in, we need to calculate the Net Present Value (NPV) for both Project A and Project B using the firm's hurdle rate of 8%. NPV is the sum of the present values of incoming and outgoing cash flows over a period of time. We will use the NPV formula for each project, discounting future cash flows back to their present value.
For Project A, the NPV calculation is as follows:
- Years 1-5: $35,000 each year
- Year 6: additional $20,000 return
For Project B, the NPV calculation is as follows:
- Years 1-5: $40,000 each year
After calculating the NPV for each project, the one with the highest positive NPV should be selected. If both projects have a negative NPV, then neither project should be selected as per the NPV rule.