Final answer:
The volume variance is $1,750.
Step-by-step explanation:
The volume variance is a measure of the difference between the budgeted fixed overhead costs and the actual fixed overhead costs, based on the standard machine-hours allowed for the actual output. In this case, the budgeted fixed overhead costs are $240,810 based on a normal level of activity of 6,900 machine-hours. The actual fixed overhead costs were $245,640 and the standard machine-hours allowed for the actual output were 6,950 machine-hours.
To calculate the volume variance, we can use the following formula:
Volume Variance = (Actual Machine-Hours - Standard Machine-Hours) * Budgeted Fixed Overhead Rate
Substituting the given values:
Volume Variance = (6,950 - 6,900) * ($240,810 / 6,900)
Simplifying,
Volume Variance = 50 * $35 = $1,750