The maximum weeks by which the project can be reduced by crashing = 8 weeks.

User Gandi
by
7.2k points

1 Answer

4 votes

Final answer:

The subject of this question is Project Management and the maximum weeks the project can be reduced by crashing. Crashing is a technique used to accelerate a project.

Step-by-step explanation:

The subject of this question is Project Management as it pertains to the maximum weeks the project can be reduced by crashing.

In Project Management, crashing is a technique used to accelerate a project by adding resources to critical activities. The maximum amount of time by which a project can be reduced through crashing is known as the crash time, which in this case is 8 weeks.

To calculate the crash time, you need to determine the critical path of the project using a network diagram and then identify the activities that can be crashed without affecting the overall project duration. By crashing these activities, the project duration can be reduced by a maximum of 8 weeks.