Operational manuals, warranties, guarantees, and as-built drawings are generally provided to the owner during which phase of the project?

User Bkjvbx
by
8.0k points

1 Answer

4 votes

Final answer:

Operational manuals, warranties, guarantees, and as-built drawings are provided to the owner during the closeout phase of the project, which follows the completion of the main construction or project work. These documents are final records of the work completed and contain maintenance and operation details, as well as contractual warranties and guarantees.

Step-by-step explanation:

Operational manuals, warranties, guarantees, and as-built drawings are generally provided to the owner during the closeout phase of the project. This phase occurs after the main construction or project work has been completed. At this point, an architect who has developed the project, similar to one planning a major office building, would be responsible for handing over these important documents. These items serve as a record of the work completed and provide the owner with important information on maintenance and the operation of the building's systems, as well as any warranties and guarantees on materials and workmanship that were part of the contractual agreement.



Traditionally, during the project, the design and construction teams move through stages that include initial research, ideation, selection of details, and finally implementation. Throughout this process, regular updates to documentation such as drawings and specifications may occur. However, it is only at the end of the project that all final documents, including any as-built drawings that detail the constructed building as it stands, are compiled and finalized. The as-built drawings and warranties provided will reflect any changes made during the construction phase, giving the owner an accurate record of the completed project.