In a BPMN activity diagram, which of the following represent a valid use for an intermediate timer event?

A. Represent a time delay
B. Indicates a delay to a specific date/time
C. Indicates a delay to a relative date, such as next Thursday
D. All of these choices are correct`

User Asym
by
7.7k points

1 Answer

5 votes

In a BPMN activity diagram, the option that represents a valid use for an intermediate timer event is D. All of these choices are correct`

What happens in the BPMN activity diagram?

Intermediate timer events are often used to model time delays within a business process. They indicate that there is a specific waiting period before the process can proceed.

Intermediate timer events can also be used to indicate a delay until a specific date and time in the future. This allows you to schedule activities or events at precise moments in a process.

These events can represent delays to relative dates, such as a certain number of hours, days, or weeks in the future, or specific days of the week like "next Thursday." This flexibility is useful for modeling processes that involve time-based conditions.