Which of the following is NOT a project constraint?

1) the budget
2) the customer requirements
3) the schedule
4) the technical specifications

User Saranga A
by
7.0k points

1 Answer

6 votes

Final answer:

A project constraint is a limitation or condition that must be satisfied by a design. The customer requirements is NOT a project constraint, as it represents the goals and expectations set forth by the customer, rather than a limitation or condition that must be met.

Step-by-step explanation:

A project constraint is a limitation or condition that must be satisfied by a design. The constraints help define the boundaries within which a project must be completed. In the given options, the customer requirements is NOT a project constraint, as it represents the goals and expectations set forth by the customer, rather than a limitation or condition that must be met.

User Tandra
by
7.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories