Which of the following is not considered to be a characteristic of a project?

1) An established objective
2) A clear beginning and end
3) Complex tasks
4) Only for internal use
5) Never been done before

1 Answer

5 votes

Final answer:

The characteristic of a project that is not considered is whether it is only for internal use.

Step-by-step explanation:

The correct answer is 4) Only for internal use. This is because a project can be conducted for internal or external purposes. It is not limited to being used solely internally.

The seven characteristics of successful projects are clear objectives, effective planning, reliable resources, proper control, communication, collaboration, and flexibility. Clear objectives are the main goal of the project that must be well-defined and understood by all stakeholders.

There are many ways to classify a project such as: By size (cost, duration, team, business value, number of departments affected, and so on) By type (new, maintenance, upgrade, strategic, tactical, operational) By application (software development, new product development, equipment installation.

Successful projects are those that 1) meet business requirements, 2) are delivered and maintained on schedule, 3) are delivered and maintained within budget, and 4) deliver the expected business value and return on investment.