Final answer:
The network logic stage comes after the sequence stage when producing a schedule.
Step-by-step explanation:
The statement provided is False.
In project management, the network logic stage comes after the sequence stage when producing a schedule.
In the sequence stage, the project is divided into tasks, and the relationships between these tasks are determined. Then, in the network logic stage, a network diagram is created, which shows the dependencies between the tasks and helps in determining the project schedule.