The list of all activities of a project with intended start and end dates linked by dependencies and constraints of a project best defines?

1) project calendar.
2) business case.
3) project schedule.
4) project scope.

User Lammyalex
by
8.2k points

1 Answer

3 votes

Final answer:

The correct answer is a project schedule, which outlines all project activities, their start and end dates, and the dependencies and constraints linking them.

Step-by-step explanation:

The list of all activities of a project, with intended start and end dates that are linked by dependencies and constraints, is best defined as a project schedule. This detailed schedule is a crucial part of project management that outlines the timing of tasks that need to be performed and their respective deadlines. It ensures that everyone involved in the project is aware of what needs to be accomplished and by when, enabling effective coordination and efficient use of resources.