Final launch documents are an output associated with the closure phase. True or False?

1 Answer

4 votes

Final answer:

The statement is false because final launch documents are usually associated with the execution phase of a project, not the closure phase. The closure phase involves finalizing activities and formal project closeout.

Step-by-step explanation:

The statement that final launch documents are an output associated with the closure phase is False. In project management, the closure phase is associated with wrapping up the project. This involves finalizing all activities, handing over deliverables, obtaining necessary approvals, releasing project resources, and formally closing out the project. The key outputs of this phase include project closure report and lessons learned document, not launch documents. Final launch documents would typically be associated with the execution phase of the project, where the actual 'launch' or delivery of the project's product, service, or result takes place.

It's essential to understand these distinctions as part of the project management process because they inform the duties and responsibilities of the project team at each stage of the project life cycle. Confusing these could lead to significant project management challenges.

User Florian Mertens
by
7.1k points