John works as a project manager for uCertify Inc. He's starting a new project. He needs to define the project objectives and develop the course of action required to attain those objectives. Under which of the following process groups does this come?

1) Executing
2) Monitor / Controlling
3) Initiating
4) Planning

1 Answer

3 votes

Final answer:

The project objectives and course of action are defined in the Initiating process group.

Step-by-step explanation:

The given scenario describes the initial phase of a project where the project manager needs to define the project objectives and develop the course of action required to attain those objectives. This phase is known as the Initiating process group in project management.