Which of the following is NOT an example of a cause for a project risk?

1) Limited team members to complete the project work
2) Work permit requirements
3) Quality assurance programs within the company
4) Schedule constraints on the project

1 Answer

5 votes

Final answer:

Qualify assurance programs within the company are not an example of a cause for a project risk.

Step-by-step explanation:

The correct answer is 3) Quality assurance programs within the company. Quality assurance programs are put in place to mitigate project risks, not cause them. These programs are designed to ensure that quality standards are met and that potential issues are identified and addressed early in the project. They are not a cause of project risks, but rather a way to minimize them. For example, a quality assurance program may involve regular inspections and testing to identify any defects or weaknesses in a product, which can help prevent problems and mitigate risks.