Which of these is an example of an internal stakeholder who would be impacted by the project process?

1) Project manager
2) Competitor
3) Customer
4) Supplier

User NomanJaved
by
7.2k points

1 Answer

3 votes

Final answer:

An internal stakeholder impacted by the project process is the Project Manager, as they are intimately involved in managing a project within an organization.

Step-by-step explanation:

The example of an internal stakeholder who would be impacted by the project process is the Project manager. A project manager is inherently an internal part of an organization, managing and being accountable for the project's success or failure, which directly affects the outcomes for the company. In contrast, competitors, customers, and suppliers are typically considered external stakeholders as they are not part of the organization's internal workings but have a stake in the project's outcomes from an external standpoint.