Final answer:
The NPV of the project is $62,509.24.
Step-by-step explanation:
To calculate the NPV of the project, we need to determine the cash flows and discount them to present value. The initial investment is $1,147,000, which is the cost of the new system. The annual cost savings are $333,250 before taxes, but since there is a 21% tax rate, the after-tax cash flow is $333,250 * (1 - 0.21) = $263,677.50. We also need to consider the salvage value of $111,600 at the end of 5 years.
Using the formula for NPV:
NPV = (Initial Investment + Annual Cash Flows) * Discount Factor - Salvage Value
Discount factor = 1 - (1 + required return rate) ^ -n, where n is the number of years.
Calculating the NPV:
NPV = ($1,147,000 + $263,677.50 * ((1 - (1 + 0.2) ^ -5) / 0.2)) - $111,600 = $62,509.24
Therefore, the NPV of this project is $62,509.24.