Schapp corporation keeps careful track of the time required to fill orders. the times recorded for a particular order appear below: hours move time2.7 wait time10.5 queue time6.9 process time1.6 inspection time0.5 the throughput time was

User Naoko
by
8.2k points

1 Answer

2 votes

Final answer:

To find the throughput time, one must add all the phase times together: Move time (2.7 hours), Wait time (10.5 hours), Queue time (6.9 hours), Process time (1.6 hours), and Inspection time (0.5 hours). The total sum is the throughput time.

Step-by-step explanation:

The student's question relates to the calculation of throughput time, a key concept in operations management and process analysis. Throughput time is the total time it takes for an order to be completed, including all phases of production from the initiation of the order to its delivery. To calculate it, you would simply sum up all the individual times provided for the different phases:

  • Move time: 2.7 hours
  • Wait time: 10.5 hours
  • Queue time: 6.9 hours
  • Process time: 1.6 hours
  • Inspection time: 0.5 hours

Throughput time = Move time + Wait time + Queue time + Process time + Inspection time.