Final answer:
To compute the activity rate for each activity using activity-based costing, divide the budgeted cost for each activity by its corresponding cost driver usage. The activity rates are $18 per square foot for factory services, $23 per setup for setup activities, and $15 per unit inspected for quality control.
Step-by-step explanation:
To compute the activity rate for each activity using activity-based costing, we need to divide the budgeted cost for each activity by its corresponding cost driver usage. Let's calculate the activity rate for each:
Factory Services:
Activity rate = Budgeted cost / Budgeted activity usage = $104,400 / 5,800 square feet = $18 per square foot
Setup:
Activity rate = Budgeted cost / Budgeted activity usage = $11,500 / 500 setups = $23 per setup
Quality Control:
Activity rate = Budgeted cost / Budgeted activity usage = $116,250 / 7,750 units inspected = $15 per unit inspected