If an agency requires 20% of the total project cost as cost sharing and the proposal is requesting $200,000 from the agency, what is the additional amount that the institution much cost share?

a. $40,000
b. $50,000
c. $100,000
d. $220,000

1 Answer

2 votes

Final answer:

The institution must cost share an additional $40,000, which is 20% of the $200,000 requested from the agency.

Step-by-step explanation:

If an agency requires 20% of the total project cost as cost sharing, and the proposal is requesting $200,000 from the agency, to find the additional amount that the institution must cost share, you would calculate 20% of the $200,000 request.

This calculation can be done by multiplying $200,000 by 0.20 (which is the percentage in decimal form).

So, the additional amount for cost sharing would be $200,000 * 0.20 = $40,000.

Therefore, the answer is a. $40,000.