A particular RFP from the U.S. Department of Energy requires a 20% cost share on Total Project

Costs (which include agency funds and the required cost share funds). If the agency funds total
$1,500,000 then the required cost share amount is:
a. $300,000
b. $375,000
c. $400,000
d. $425,000

User Muqito
by
7.2k points

1 Answer

2 votes

Final answer:

The required cost share amount for a project with agency funds of $1,500,000 and a 20% cost share requirement is $375,000, which is option (b).

Step-by-step explanation:

The question posed relates to the calculation of the required cost share amount for a project based on a given total project cost and a specified percentage for cost sharing. If the U.S. Department of Energy grants agency funds totaling $1,500,000 and requires a 20% cost share on the Total Project Costs, the calculation is as follows:

Total Project Cost = Agency Funds + Required Cost Share

100% of Total Project Cost = Agency Funds (which is 80% of Total Project Cost because the remaining 20% is the required cost share)

Thus, $1,500,000 is 80% of the Total Project Cost.

To find the Total Project Cost (100%), we calculate:

Total Project Cost = Agency Funds / 0.80

Total Project Cost = $1,500,000 / 0.80

Total Project Cost = $1,875,000

The Required Cost Share Amount is 20% of the Total Project Cost:

Required Cost Share Amount = Total Project Cost × 0.20

Required Cost Share Amount = $1,875,000 × 0.20

Required Cost Share Amount = $375,000

Therefore, the correct answer is (b) $375,000.