Which project management approach is used when resources cannot be increased to meet deadlines?

Critical chain project Management
Six Sigma Project Management
Lean Project Management

User Termi
by
7.5k points

1 Answer

1 vote

Final answer:

Critical Chain Project Management is the approach used when resources cannot be increased to align with deadlines, managing resources based on the critical chain and utilizing buffers.

Step-by-step explanation:

The project management approach used when resources cannot be increased to meet deadlines is Critical Chain Project Management (CCPM). CCPM focuses on the management of resources and prioritizes tasks based on the critical chain, which is the sequence of both precedence- and resource-dependent tasks that determine the project's duration. By identifying and managing bottlenecks and incorporating buffer times to account for uncertainties and delays, CCPM allows for the completion of projects within the constraints of available resources and time.

User SharpLu
by
7.4k points