104k views
2 votes
Estimating activity resources is a function of cost management.

a. True
b. False

User Trafalgarx
by
7.7k points

1 Answer

7 votes

Final answer:

Estimating activity resources is not a function of cost management. It is a part of the project management process that involves identifying and quantifying the resources needed for each activity in a project.

Step-by-step explanation:

The correct answer is False. Estimating activity resources is not a function of cost management. It is a part of the project management process that involves identifying and quantifying the resources needed for each activity in a project. This includes determining the types and quantities of materials, equipment, and labor required. Cost management, on the other hand, focuses on estimating, budgeting, and controlling the costs of a project.

User Lika
by
7.6k points