As a project manager, you're identifying task dependencies. Task B cannot start until Task A is complete. Which type of dependency does this situation represent?

a. Finish to Start (FS)
b. Start to Finish (SF)
c. Finish to Finish (FF)
d. Start to Start (SS)

User Kozydot
by
7.7k points

1 Answer

1 vote

Final answer:

In project management, Task B not being able to start until Task A is completed is known as a Finish to Start (FS) dependency, which is critical for managing the project timeline.

Step-by-step explanation:

When a project manager is identifying task dependencies and finds that Task B cannot start until Task A is complete, this situation represents a Finish to Start (FS) dependency. This is the most common type of dependency in project management. In a Finish to Start relationship, the start of the successor task (in this case, Task B) depends on the completion of its predecessor task (Task A). It's essential for creating a logical sequence of tasks and managing the project timeline effectively.