Final answer:
The firm's ATC is $27 and the total cost is $270.
Step-by-step explanation:
To find the firm's average total cost (ATC), we need to calculate it by dividing the total cost by the total quantity produced. Given that the average variable cost (AVC) is $22 and the average fixed cost (AFC) is $5, we can calculate the ATC using the formula:
ATC = AVC + AFC
ATC = $22 + $5 = $27
Therefore, the firm's ATC is $27, which is not one of the options listed in the question.
To calculate the firm's total cost, we need to multiply the ATC by the quantity produced:
Total Cost = ATC * Quantity
Total Cost = $27 * 10 = $270
Therefore, the firm's total cost is $270, which is option C in the question.