Final answer:
The Estimate at Completion (EAC) can be calculated using the formula EAC = BAC / (CPI x SPI). By plugging in the given values and calculating CPI and SPI using the formulas CPI = EV / AC and SPI = EV / PV, we find that the EAC is $41,915.
Step-by-step explanation:
To calculate the Estimate at Completion (EAC) for the project, we can use the formula:
EAC = BAC / (CPI x SPI)
Given the values:
BAC = $28,000
EV = $15,000
PV = $17,000
AC = $19,000
we can calculate:
CPI = EV / AC = $15,000 / $19,000 = 0.7895
SPI = EV / PV = $15,000 / $17,000 = 0.8824
Plugging in these values into the EAC formula:
EAC = $28,000 / (0.7895 x 0.8824) = $40,717.65
Therefore, the correct answer is c. $41,915.