Develop a Statement of Work (SOW) for a work package that is part of a WBS element of a construction project that is going to be subcontracted.

Please provide the WBS for your project in the Appendix.
State any and all assumptions that you are making as
a. part of the SOW.
b. Elements of SOW
c. General scope of the work
d. Objectives and related background
e. Contractor’s tasks
f. Contractor end-item performance requirements
g. Reference to related studies, documentation, and specifications
h. Data items (documentation)
i.Support equipment for contract end item
j. Customer-furnished property, facilities, equipment, and services
k. Customer-furnished documentation
l. Schedule of performance
m. Exhibits, attachments, and appendices

User Altareos
by
7.4k points

1 Answer

1 vote

Final answer:

A Statement of Work (SOW) for a construction project that will be subcontracted includes a detailed scope of work, tasks, performance standards, relevant documentation, equipment needs, customer-furnished items, and a performance schedule.

Step-by-step explanation:

Statement of Work (SOW) for Subcontracted Construction Work Package

Statement of Work (SOW) is a document that clearly defines the scope of work to be performed by a contractor. It will typically include detailed descriptions of the work that needs to be completed, as well as the deliverables or end items that are expected from the contractor. The SOW for a construction project that will be subcontracted is outlined below:

a. Assumptions

The subcontractor has all necessary licenses and insurances.

All necessary permits and approvals have been obtained.

b. Elements of SOW

General scope of the work including all necessary labor and materials to complete the specified work package.

Objectives of the work package, such as improving infrastructure, within the associated construction project.

Detailed list of contractor's tasks to fulfill the scope of the project.

Performance requirements and quality standards for the end-item.

c. Reference Documentation

Applicable building codes and safety regulations.

Engineering drawings and project specifications provided by the hiring company.

d. Data Items and Support Equipment

List of documentation such as progress reports and final inspection reports that the contractor is expected to provide.

Equipment necessary to carry out tasks, which may be sourced by the contractor or provided by the client.

e. Schedule of Performance

A timeline that outlines when specific phases of the work package are to begin and end.

The Work Breakdown Structure (WBS), which details the entire scope of the construction project, will be provided in the appendices section of the full project documentation.