Final answer:
The schedule variance is 11%, the schedule performance index is 1.208, and the cost performance index is 0.588.
Step-by-step explanation:
The schedule variance (SV) measures the difference between the planned progress and the actual progress of a project. To calculate the SV, you subtract the planned completion percentage from the actual completion percentage: SV = Actual Completion - Planned Completion.
In this case, the planned completion of the third activity was 53%, but the actual completion is 64%, so the SV is:
SV = 64% - 53% = 11%.
The schedule performance index (SPI) measures how efficiently the project is progressing in relation to the planned schedule. To calculate the SPI, you divide the actual completion percentage by the planned completion percentage: SPI = Actual Completion / Planned Completion.
In this case, the SPI is:
SPI = 64% / 53% ≈ 1.208 (rounded to three decimal places).
The cost performance index (CPI) measures how efficiently the project is using its budget. To calculate the CPI, you divide the earned value (actual cost) by the planned value (budgeted cost): CPI = Earned Value / Planned Value.
In this case, the earned value for the superstructure is $5,003,000 and the planned value is $8,503,000, so the CPI is:
CPI = $5,003,000 / $8,503,000 ≈ 0.588 (rounded to three decimal places).