Final answer:
The economic order quantity (EOQ) for the given values is 179.
Step-by-step explanation:
The economic order quantity (EOQ) can be calculated using the formula:
EOQ = √((2 * demand * setup cost) / holding cost)
Substituting the given values, EOQ = √((2 * 2000 * 80) / 10) = √32000 = 179
Therefore, the economic order quantity is 179.