Final answer:
Activity-based costing assigns costs to different activities or cost drivers. The total cost of the Kanejob can be calculated using the direct labor cost, CPU minutes, and legal hours.
Step-by-step explanation:
In activity-based costing, the total cost of a job is calculated by assigning costs to different activities or cost drivers. In this case, the direct labor cost of $1,200 is the cost driver. The CPU minutes and legal hours are used to allocate the cost of direct labor to the job. If we assume a predetermined overhead rate of $2 per CPU minute and $60 per legal hour, then the total cost of the Kanejob would be:
Total cost = Direct labor cost + (CPU minutes × overhead rate) + (Legal hours × overhead rate)
Total cost = $1,200 + (600 × $2) + (1 × $60) = $1,200 + $1,200 + $60 = $2,460
Therefore, the correct answer is $2,460.