201k views
0 votes
Which of the following process groups involves coordinating people and resources, managing stakeholder expectations, as well as integrating and performing the activities of the project in accordance with the project management plan?

a) Initiating
b) Planning
c) Executing
d) Monitoring and Controlling

1 Answer

2 votes

Final answer:

The executing process group involves coordinating people and resources, managing stakeholder expectations, and integrating and performing project activities.

Step-by-step explanation:

The process group that involves coordinating people and resources, managing stakeholder expectations, as well as integrating and performing the activities of the project in accordance with the project management plan is the Executing process group.

User Ggmkp
by
6.7k points