A manager using a force-coercion strategy is most likely relying on the power of ____________ to bring about planning change.

1 Answer

2 votes

Final answer:

A manager using a force-coercion strategy relies on intimidation to bring about planning change.

Step-by-step explanation:

A manager using a force-coercion strategy is most likely relying on the power of intimidation to bring about planning change. Force-coercion strategies involve using threats, intimidation, and the power to enforce punishment in order to achieve desired outcomes.