Which statement is correct about spending effort in small projects?

A. Small projects typically spend 5 to 7 percent of their total effort on requirements worK
B. Small projects typically spend 7 to 8 percent of their total effort on requirements work
C. Small projects typically spend 15 to 18 percent of their total effort on requirements work
D. Small projects typically spend 25 to 30 percent of their total effort on requirements work

1 Answer

5 votes

Final answer:

Small projects typically allocate 15 to 18 percent of their total effort to requirements work, a critical stage in project planning and execution.

Step-by-step explanation:

When it comes to the efficiency and effectiveness of project management, understanding how effort is distributed across a project's lifecycle is essential. In the case of small projects, a significant amount of effort is typically allocated to requirements work. Although there isn't an exact one-size-fits-all percentage, a commonly accepted range of effort spent on requirements work for small projects is 15 to 18 percent of the total effort. This reflects the importance of adequately scoping and understanding the project's needs before diving into execution. Comparatively, less complex and smaller scale projects might spend less effort on planning and more on execution, whereas larger projects may require more extensive requirements work and planning time.

User Amaster
by
9.0k points