To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?

Question Progress Homework Progress 88 / 213 Marks To complete a task in 16 days a-example-1
User Shilaghae
by
8.7k points

1 Answer

4 votes

Answer:

15 Days

Explanation:

Formula:

M1D1H1=M2D2H2