Final answer:
The planned allowance for sampling risk is 5.5 percent, calculated by subtracting the estimated population deviation rate of 2.5 percent from the computed upper deviation rate of 8 percent.
Step-by-step explanation:
The auditor's planned allowance for sampling risk is the difference between the estimated population deviation rate and the computed upper deviation rate. In this case, the auditor estimated from past experience that about 2.5 percent of the sales invoices lacked approval (estimated population deviation rate), and the computed upper deviation rate from the sample was 8 percent.
Therefore, the planned allowance for sampling risk is the computed upper deviation rate minus the estimated population deviation rate, which equals 8 percent - 2.5 percent = 5.5 percent. The correct answer to the question is: 5 ½ percent.