Final answer:
The total cost of Job X-10 is calculated by adding the beginning balance, materials requisitioned, direct labor cost, and overhead (which is 50% of labor cost). The total cost comes to $11,750.
Step-by-step explanation:
To calculate the total cost of Job X-10, you must first sum the beginning balance, the cost of materials requisitioned, the direct labor cost, and the overhead. The overhead is calculated as 50% of direct labor cost. Here are the detailed computations:
- Begin with the beginning balance: $1,500
- Add the cost of materials requisitioned: $5,000
- Add the direct labor cost: $3,500
- Calculate the overhead, which is 50% of the direct labor cost: 0.50 Ă— $3,500 = $1,750
- Sum all the above figures to find the total cost of Job X-10: $1,500 + $5,000 + $3,500 + $1,750 = $11,750
The total cost of Job X-10 is $11,750.