182k views
4 votes
Concord is contemplating a capital project costing $32838. The project will provide annual cost savings of $12600 for 3 years and have a salvage value of $2000. The company's required rate of return is 10%. The company uses straight-line depreciation. What is the present value (PV) of the project?

1) $32838
2) $12600
3) $2000
4) Cannot be determined

User Rajmohan
by
8.9k points

1 Answer

2 votes

The present value (PV) of the project can be calculated using the formula: PV = [Annual cost savings / (1 + Required rate of return)] + [Salvage value / (1 + Required rate of return)^3]. Using the given values, the PV of the project is calculated as: PV = [12600 / (1 + 0.10)] + [2000 / (1 + 0.10)^3]. The PV of the project is $10,909.09.

The present value (PV) of the project can be calculated using the formula:

PV = [Annual cost savings / (1 + Required rate of return)] + [Salvage value / (1 + Required rate of return)^3]

Using the given values, the PV of the project is calculated as:

PV = [12600 / (1 + 0.10)] + [2000 / (1 + 0.10)^3]

Simplifying the calculation gives a PV of $10,909.09. Therefore, the PV of the project is not one of the options provided.

User Trylks
by
8.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.