The present value (PV) of the project can be calculated using the formula: PV = [Annual cost savings / (1 + Required rate of return)] + [Salvage value / (1 + Required rate of return)^3]. Using the given values, the PV of the project is calculated as: PV = [12600 / (1 + 0.10)] + [2000 / (1 + 0.10)^3]. The PV of the project is $10,909.09.
The present value (PV) of the project can be calculated using the formula:
PV = [Annual cost savings / (1 + Required rate of return)] + [Salvage value / (1 + Required rate of return)^3]
Using the given values, the PV of the project is calculated as:
PV = [12600 / (1 + 0.10)] + [2000 / (1 + 0.10)^3]
Simplifying the calculation gives a PV of $10,909.09. Therefore, the PV of the project is not one of the options provided.