Herschel has been assigned as the project manager for an upcoming project. The project's final deliverable is well-understood, but the product must be completely finished before it can be used by customers. Which life cycle approach should Herschel use on this project?

1) an iterative and incremental approach
2) an adaptive approach
3) a predictive approach
4) an Agile approach

User BlackStork
by
8.1k points

1 Answer

2 votes

Final answer:

Herschel should use 1) an iterative and incremental approach for this project. Hence, option 1) is correct.

Step-by-step explanation:

Herschel should use an iterative and incremental approach for this project. This approach involves breaking down the project into smaller, manageable parts or iterations, with each iteration building upon the previous one.

Each iteration allows for feedback and adjustments, which can help ensure the final deliverable meets customer requirements. The iterative and incremental approach is often used when the final product is well-understood, but there may be uncertainties or changes in requirements along the way.