Project managers wield more authority in a(n) ________ structure than in a(n) ________ structure.

1) balanced matrix, PMO
2) multidivisional, weak matrix
3) balanced matrix, strong matrix
4) virtual, multidivisional

User Sarema
by
8.0k points

1 Answer

1 vote

Final answer:

Project managers have more authority in a balanced matrix structure than in a weak matrix structure.

Step-by-step explanation:

In a balanced matrix structure, project managers have more authority than in a weak matrix structure. In a balanced matrix structure, there is a balance of power between the project manager and the functional managers, meaning that the project manager has more control over the project and its resources. On the other hand, in a weak matrix structure, the functional managers have more authority, and the project manager's role is more limited.