Final answer:
To calculate the economic order quantity (EOQ), use the formula EOQ = √((2 * Annual Demand * Ordering Cost) / Holding Cost). The EOQ in this case is approximately 154.45 units. To determine the reorder point for components, use the formula Reorder Point = Demand per day * Lead time. The reorder point in this case is 7200 units.
Step-by-step explanation:
To calculate the economic order quantity (EOQ), we can use the formula:
EOQ = √((2 * Annual Demand * Ordering Cost) / Holding Cost)
Using the given information:
Annual Demand = 900 units
Ordering Cost = $47.35
Holding Cost = 15% of $23.75 = $3.56
Substituting these values into the formula:
EOQ = √((2 * 900 * 47.35) / 3.56) = √(84870 / 3.56) ≈ √(23852.81) ≈ 154.45 units
Therefore, the economic order quantity is approximately 154.45 units.
To determine the reorder point for components, we can use the formula:
Reorder Point = Demand per day * Lead time
Using the given information:
Demand per day = Monthly demand / Number of days in a month = 900 / 30 = 30 units
Lead time = Number of days the supplier takes to deliver = 240 days
Substituting these values into the formula:
Reorder Point = 30 * 240 = 7200 units
Therefore, the reorder point for components is 7200 units.