105k views
3 votes
ABC Inc. orders components for distribution at a monthly demand of 900 units. Holding costs are 15% of the unit cost of $23.75. The ordering cost is $47.35. The company operates 240 days per year.

a) Calculate the economic order quantity (EOQ)
b) Determine the reorder point for components

User Thomsen
by
7.9k points

1 Answer

0 votes

Final answer:

To calculate the economic order quantity (EOQ), use the formula EOQ = √((2 * Annual Demand * Ordering Cost) / Holding Cost). The EOQ in this case is approximately 154.45 units. To determine the reorder point for components, use the formula Reorder Point = Demand per day * Lead time. The reorder point in this case is 7200 units.

Step-by-step explanation:

To calculate the economic order quantity (EOQ), we can use the formula:

EOQ = √((2 * Annual Demand * Ordering Cost) / Holding Cost)

Using the given information:

Annual Demand = 900 units

Ordering Cost = $47.35

Holding Cost = 15% of $23.75 = $3.56

Substituting these values into the formula:

EOQ = √((2 * 900 * 47.35) / 3.56) = √(84870 / 3.56) ≈ √(23852.81) ≈ 154.45 units

Therefore, the economic order quantity is approximately 154.45 units.

To determine the reorder point for components, we can use the formula:

Reorder Point = Demand per day * Lead time

Using the given information:

Demand per day = Monthly demand / Number of days in a month = 900 / 30 = 30 units

Lead time = Number of days the supplier takes to deliver = 240 days

Substituting these values into the formula:

Reorder Point = 30 * 240 = 7200 units

Therefore, the reorder point for components is 7200 units.

User Zatatatata
by
7.6k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.