Final answer:
The net present value (NPV) of the project is -$5,373.
None of the given options is correct
Step-by-step explanation:
The net present value (NPV) of a project can be calculated by discounting the projected cash flows to their present values and then summing them up.
For Year 0, the cash flow is -$50,000. Since it is the initial investment, it has no discounting applied to it.
- For Year 1, the cash flow is $15,000. Discounted to Year 0, it becomes $12,396.
- For Year 2, the cash flow is $20,000. Discounted to Year 0, it becomes $14,050.
- For Year 3, the cash flow is $30,000. Discounted to Year 0, it becomes $18,181.
To calculate the NPV, we sum up the present values: -$50,000 + $12,396 + $14,050 + $18,181 = -$5,373.
Therefore, the net present value (NPV) of the project is -$5,373.
None of the given options is correct