Final answer:
The correct answer is b. 1st month failure = 90%, 2nd month failure = 80%, 3rd month failure = 50%.
Step-by-step explanation:
The correct answer is b. 1st month failure = 90%, 2nd month failure = 80%, 3rd month failure = 50%.
Based on the information given in the question, the failure rates for each month are as follows:
- 1st month failure = 10%
- 2nd month failure = 20% (if the machine completes its first month)
- 3rd month failure = 50% (if the machine completes its second month)
Therefore, the failure rates for the three months are 10%, 20%, and 50% respectively. To determine the success rates for each month, subtract the failure rates from 100%:
- 1st month success = 100% - 10% = 90%
- 2nd month success = 100% - 20% = 80%
- 3rd month success = 100% - 50% = 50%
So, the correct answer is (b) 1st month failure = 90%, 2nd month failure = 80%, 3rd month failure = 50%.