38.4k views
1 vote
What three types of data does Microsoft Project use to compute each assignment’s cost value?

User Sbodd
by
7.4k points

1 Answer

3 votes

Microsoft Project uses three types of data to compute each assignment's cost value: Average Total Cost, Average Variable Cost, and Marginal Cost.

Average Total Cost: This is the total cost of all resources used for an assignment divided by the number of units or hours of work completed.

Average Variable Cost: This is the cost of only the variable resources used for an assignment divided by the number of units or hours of work completed.

Marginal Cost: This is the additional cost incurred by producing one extra unit or completing one extra hour of work for an assignment.

User Oscarm
by
7.0k points