Final answer:
Using the cost-to-cost approach, Heineken recognizes revenue on the construction project as the project progresses and costs are incurred.
Step-by-step explanation:
The subject of this question is Business and the grade level is College.
Using the cost-to-cost approach, Heineken Co. recognizes revenue on the construction project as the project progresses and costs are incurred. In 2019, Heineken incurred $36 million in costs. By the end of 2019, the revenue recognized would be equal to the costs incurred, so $36 million would be recognized as revenue in 2019.
In 2020, Heineken incurred $58.5 million in costs. Since $36 million had already been recognized in 2019, the remaining costs in 2020 would be $58.5 million - $36 million = $22.5 million. Therefore, $22.5 million would be recognized as revenue in 2020.