203k views
1 vote
Heineken Co. began a construction project in 2019 at a total contract price of $150 million. The project is scheduled for completion by 2021. During 2019, Heineken incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. In 2020, Heineken incurred costs of $58.5 million and estimated an additional $40.5 million in costs to complete the project. Heineken recognizes revenue on all contracts over time, as the project is being completed by using the cost-to-cost approach.

A) $36 million is recognized as revenue in 2019
B) $58.5 million is recognized as revenue in 2020
C) Total contract price is $100 million
D) The project will be completed in 2023

1 Answer

4 votes

Final answer:

Using the cost-to-cost approach, Heineken recognizes revenue on the construction project as the project progresses and costs are incurred.

Step-by-step explanation:

The subject of this question is Business and the grade level is College.

Using the cost-to-cost approach, Heineken Co. recognizes revenue on the construction project as the project progresses and costs are incurred. In 2019, Heineken incurred $36 million in costs. By the end of 2019, the revenue recognized would be equal to the costs incurred, so $36 million would be recognized as revenue in 2019.

In 2020, Heineken incurred $58.5 million in costs. Since $36 million had already been recognized in 2019, the remaining costs in 2020 would be $58.5 million - $36 million = $22.5 million. Therefore, $22.5 million would be recognized as revenue in 2020.

User Bojan Hrnkas
by
7.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories