Calculate how many cubic yards of concrete are needed for a trench footing 24' x 24' x 4' deep by 1' wide.

14 cubic yards
14.22 cubic yards
15 cubic yards
15.5 cubic yards

User McGuile
by
7.5k points

1 Answer

4 votes

Final answer:

The correct volume of concrete needed for the given trench footing dimensions is approximately 3.554 cubic yards, none of the student-provided answer choices are correct.

Step-by-step explanation:

To calculate the volume of concrete needed for a trench footing that is 24 feet long, 24 feet wide, 4 feet deep, and 1 foot wide, you use the formula for the volume of a rectangular prism, which is Volume = length × width × depth.

First, convert the dimensions to yards because the question asks for the volume in cubic yards. There are 3 feet in 1 yard. Therefore, for the dimensions given in feet, you will have:

  • Length: 24 feet / 3 = 8 yards
  • Width: 1 foot / 3 ≈ 0.333 yards
  • Depth: 4 feet / 3 ≈ 1.333 yards

So the volume is:

V = 8 yards × 0.333 yards × 1.333 yards ≈ 3.554 cubic yards