An architect is drafting a project manual for a large hotel and casino project. Which of the following procedures and administrative protocols should the architect include in Division 01?

User Shibumi
by
7.1k points

1 Answer

1 vote

Final answer:

Division 01 of a project manual for an architectural project such as a large hotel and casino includes procedures for contractual relationships, project management, and administrative protocols to guide the construction process.

Step-by-step explanation:

An architect working on a large hotel and casino project would include various procedures and administrative protocols in Division 01 of the project manual. Division 01 is a core section that outlines the general requirements for the construction process and provides a framework for the management of the project. Key elements to be included are contractual relationships, administrative procedures, quality control measures, submittal processes, and project management protocols.

For example, it could detail the submission of shop drawings, the process of requesting information, the handling of payments, and the coordination of scheduling and material delivery. Furthermore, Division 01 is integral for setting up the rules of operation among various stakeholders, outlining safety programs, and defining environmental protection measures.

User Nealkernohan