129k views
1 vote
Given the following data for Project M calculate the NPV of the project. Cash flow in nominal terms: Real discount rate= 5% Nominal discount rate = 10% Co -100 C₁ 75 C₂ 60​

1 Answer

7 votes

Final answer:

The Net Present Value (NPV) of Project M is calculated using the nominal discount rate and the provided cash flows. After discounting each cash flow to its present value, the total NPV of Project M is 17.77, indicating a positive return for the project.

Step-by-step explanation:

To calculate the Net Present Value (NPV) of Project M, we must discount the future cash flows back to their present value using the nominal discount rate provided, which is 10%. The cash flows are: initial investment (Co) at time 0 of -100, first year cash flow (C1) of 75, and second year cash flow (C2) of 60.

Present Value of C1: PV = C1 / (1 + r)n

= 75 / (1 + 0.10)1

= 75 / 1.10

= 68.18.

Present Value of C2: PV = C2 / (1 + r)n

= 60 / (1 + 0.10)2

= 60 / 1.21

= 49.59.

The total NPV of Project M is the sum of all present values minus the initial investment:

NPV = Co + PV of C1 + PV of C2

= -100 + 68.18 + 49.59

= 17.77.

Therefore, the NPV of Project M is 17.77, which implies the project is expected to add value to the firm as it’s positive.

User Hamed Nazaktabar
by
8.2k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.