Which Qualification protocol is carried out after the equipment is released for use?

A. Design Qualification (DQ)
B. Installation Qualification (IQ)
C. Operational Qualification (OQ
D. Performance Qualification (PQ)

User Xplat
by
7.6k points

1 Answer

7 votes

Answer:

C. Operational Qualification (OQ)

Step-by-step explanation:

After the equipment is released for use, the Operational Qualification (OQ) protocol is typically carried out. OQ is conducted to verify and document that the equipment operates as intended within its specified operating range and under normal operating conditions. This testing ensures that the equipment functions correctly and meets the necessary operational requirements before being used in production or other critical processes.