Question Progress Homework Progress 21/24 Marks To complete a task in 16 days a company needs 5 people each working for 6 hours per day. The company decides to have 8 people each working for 4 hours per day. Assuming that each person works at the same rate, how many days will the task take to complete? 71%​

User Olaj
by
7.3k points

1 Answer

5 votes

Final answer:

The task would take 30 days to complete with 8 people each working for 4 hours per day.

Step-by-step explanation:

To find out how many days it would take to complete the task with 8 people each working for 4 hours per day, we can use the formula: number of days = (number of people * number of hours per day * original number of days) / (new number of people * new number of hours per day). Plugging in the values, we get: number of days = (5 * 6 * 16) / (8 * 4) = 30.

Therefore, it would take 30 days to complete the task with 8 people each working for 4 hours per day.