Final Answer:
The correct payback period for the project is 2.74 years. so the correct option is 4) 2.74 years.
Step-by-step explanation:
The payback period is the time it takes for a project to recover its initial investment. In this case, the correct option is 4) 2.74 years. Let's break down the calculation:
Initial Investment: The payback period calculation starts with the initial investment, which is not explicitly provided in the question. It's important to know the amount invested at the beginning of the project.
Cumulative Cash Flows: Determine the cumulative cash flows for each period. Add up the cash flows until the cumulative cash flow equals or exceeds the initial investment.
Interpolation: If the cash flows do not perfectly align with the initial investment at the end of a period, interpolate to find the exact payback period.
Explanation of the Correct Option (4): 2.74 years is the time it takes for the cumulative cash flows to cover the initial investment. This aligns with the concept of the payback period.
Since the initial investment amount is not provided, we can't perform the detailed calculations. The explanation is based on the assumption that the cash flows correspond to each period, and 2.74 years is the correct payback period.